Keller assisted the client in identifying an economical approach to produce a safe working platform for the equipment while minimizing the impact on the schedule.

Keller installing wick drains for the Atlantic Wood Superfund site
Installing wick drains at the Atlantic Wood Superfund site to accelerate settlement.

The project

A 1,150-foot berth was planned for construction on the Atlantic Wood Superfund 48-acre property, which previously hosted a wood production facility. To achieve the final grade, approximately 12 feet of fill was to be placed over the existing 40-foot-deep soft marine sediments contaminated with creosote and pentachlorophenol used to preserve wood at the previous facility. An existing elevated highway supported on piles traversed the site.

The challenge

The settlement of the marine sediments would take several years, delaying future planned use of the site by a precast concrete supplier. In addition, the groundwater drainage from the soft marine sediments resulting from the fill surcharge would be contaminated. The existing bridge piling would experience down drag loading during the consolidation of the marine sediments. A solution of solidifying the contaminated material with cement to great depth would have been very costly.

The solution

Wick drains were selected as a cost-efficient solution to accelerate settlement and strength gain during the planned fill placement. The wick drains were installed through the compressible layer and connected to a pump system to collect and remove the contaminated fluid for treatment. The existing highway piling was determined to have sufficient capacity to withstand the down drag loading.

Keller worked with us to determine a revised installation methodology after encountering very soft subgrade conditions. Sevenson found Keller’s management to be very professional, insightful, knowledgeable, and beneficial to the project.
Andrew Wright
Vice President, Sevenson Environmental Services, Inc.

Project facts

Owner(s)

U.S. Army Corps of Engineers

Keller business unit(s)

Keller

Main contractor(s)

Sevenson Environmental Services, Inc.

Engineer(s)

EA Engineering, Science, and Technology, Inc., PBC